|
Diablo
Timeline Part II
1982-1996
1982
- Jan
14 PG&E fails to get a full power discharge permit from the
Regional Water Quality Control Board;
- Jan
19 The NRC ASLB holds 7 days of hearings on evacuation plans;
- Jan
Californian's for Nuclear Safeguards finalize a state wide ballot initiative
that would end nuclear power in California on economic grounds. The
initiative is killed by an L.A. industrialist, who is planning to launch
his own ballot initiative "The Nuclear Freeze" initiative;
- Feb
11 The NRC votes 3-2 to issue a notice of violation to PG&E
for making a Material False Statement;
- Mar
15 The Reedy Co. reports that two previously completed reviews of
the company's quality assurance program are flawed. Reedy goes on to
say that PG&E failed to maintain proper oversite of design and construction
of the facility prior to 1978. The 1986 CPUC investigation required
FOIA channels to gain full access to some of this review;
- Mar
18 The NRC votes 3-2 in favor of the 7.5 magnitude slip/strike seismic
design criteria;
- Mar
19 The NRC meets with PG&E executives to review the company's
management of all nuclear activities which is rated as poor;
- Mar
19 After intense public pressure, the NRC selects Teledyne to do
the Independent Design Verification Process. Controversy continues as
the new company has a previous history with PG&E and also owns PG&E
stock;
- Mar
22 PG&E retains Bechtel Power Corp. to manage the 2nd reconstruction
of the facility;
- April
23 The NRC's ASLB okays PG&E's security plans. Intervenors appeal
the decision;
- May
24 Pre-trial hearings begin for Abalone blockaders from last September's
action;
- June
11 The Cal. Water Quality Control Board over-rules their own regional
board's refusal to grant a discharge permit into the ocean. The permit
allows PG&E to waives all EPA standards for toxic discharges, with
the maximum daily release set at 2.5 billion gallons of water that is
from 20 to 100 degrees above normal;
- July
8 Repair work on the damaged breakwater begins;
- Aug
31 The NRC's ASLB says that Diablo emergency plans meet federal
standards for a full power license;
- Sept
27 County supervisors vote 3-2 to accept a proposed emergency evacuation
plan;
- Oct
1 PG&E makes its 8th revision to costs and operation. PG&E
estimates both units will cost an additional $945 million making the
combined total costs of $3,255,000,000 with operation dates for unit
1 set for 10/1/83 and unit 2 set for 4/15/84;
- Dec
8 The NRC approves a new 3 step plan for Diablo's licensing;
- Dec
8 Agents arrest a man who was plotting to plant a bomb at the reactors.
He was later released when claims were made that undercover police were
helping him;
1983
- Jan
28 Attorney General Van De Kamp replaces former Governor Jerry Brown
as an intervenor;
- Mar
8 Congressional leaders urge the NRC to be careful in its oversite
of Diablo;
- Mar
17 PG&E accepts state Water Quality Control Board discharge
limits;
- Mar
18 PG&E currently has 4,600 workers onsite that have made 5,890
modifications to pipe supports and other errors that have been found
since 1981;
- Mar
26 An SLO rally brings out 3,500 opponents of Diablo;
- April
21 The NRC appeals board orders more hearings on design quality;
- May
10 Reports of worker harassment and improper removal of repair tags
grow;
- June
16 The flood of workers is making it hard for other people to find
housing in the SLO area;
- July
19 The NRC appeals board holds hearings over sloppy work. A former
inspection supervisor states that quality control has dropped dramatically
since last winter;
- Aug
8 The NRC staff recommends that the low-power testing license be
restored;
- Sept
12 Intervenors discover an audit that contradicts PG&E testimony
about quality controls;
- Sept
17 An NRC report to Congress says that PG&E's overconfidence
led to design errors at Diablo;
- Oct
25 The NRC denies intervenor requests for hearings on quality controls
claiming the request was not up to code;
- Oct
28 NRC director Harold Denton tells the full commission that Diablo
is ready to load fuel;
- Oct
31 3 weeks of NRC hearings on design problems begin with PG&E
claiming that none of the design problems found had safety implications;
- Nov
8 The NRC votes 4-0 to restore PG&E's low-power testing license
and load nuclear fuel into unit 1;
- Nov
9 Intervenors file for an injunction against fuel loading with D.C.
Court of Appeals;
- Nov
11 The court grants the injunction against fuel loading;
- Nov
15 The court pulls the injunction and PG&E begins loading fuel;
- Nov
21 The Abalone Alliance announces plans to start a series of protests
at Diablo beginning Jan. 13th;
- Nov
30 An engineer tells the NRC that he was fired for complaining about
flawed safety reports on seismic designs. He also states that PG&E
altered records on piping systems that had failed;
- Dec
2 The NRC starts investigates allegations of hundreds of stories
about altered construction reports;
1984
- Jan
13 Abalone Alliance starts extended blockade at the Diablo front
gates. 537 people are arrested over a 4 months;
- Jan
24 Federal investigations begin of alleged activities at Diablo.
The chairman of the NRC defends the agencies behavior before Congressional
hearings;
- Feb
11 1,000 protest at Diablo while 52 are arrested;
- Feb
12 6 arrested at Diablo front gates;
- Feb
13 8 arrested at Diablo front gates--total to date 301;
- Mar
27 The NRC vote 3-2 not to give PG&E alow-power testing license
for Unit 1. Commissioners consider bringing in a 3rd party to oversee
quality assurance;
- Mar
27 A new Hosgri fault study indicates that the fault may be closer
to Diablo than previously thought;
- April
6 An NRC engineer backs down from his opposition to giving PG&E
a low-power testing license after immense internal pressure is put on
him. He says a compromise plan will fix errors before full power operations
begin;
- April
13 The NRC votes 4-1 to reinstate PG&E's low-power testing license;
- April
18 The D.C. Court of Appeals refuses to grant intervenors an injunction
on the low-power testing license;
- April
29 PG&E starts Unit 1;
- May
10 PG&E requests a $300,000,000 rate increase from the CPUC;
- May
18 The NRC proposes a $50,000 fine due to closed safety valves;
- May
26 Presidential candidate Mondale goes to SLO and makes speech against
Diablo Canyon;
- June
PG&E breaks up the Diablo quick-fix engineering group that has been
"eyeballing" repairs without engineering analysis;
- June
Mothers for Peace files 100 new cases of misleading or material
false statements, bringing the current total to 1,300;
- June
An NRC safety inspector voices concerns over 2 of 7 technical seismic
issues as well as several other safety related issues;
- June
8 The utility asks the NRC to grant them a full-power testing license
for unit 1;
- June
14 NRC officials testify before a congressional subcommittee about
Diablo licensing;
- June
21 The Government Accountability Project (GAP) asks the state Attorney
General to investigate 100 allegations of lying;
- June
28 The NRC blocks a proposal for new hearings on design and construction
flaws made by intervenors;
- June
29 The NRC appeals board reverses a 1982 ruling by the NRC that
evacuation plans be certified before operation can begin;
- June
29 PG&E makes its 9th revision to costs and operation. Total
costs jump $1.885 billion to $5,140,000,000 with an operational date
of Sept. 84 for unit 1 and May 85 for unit 2;
- July
9 11 activists are convicted for trespassing in the winter Abalone
actions;
- July
9 The NRC staff says pipe design errors found last winter won't
effect safety;
- July
11 Isa Yin resigns from the NRC inspection project in protest over
the agency's handling of safety issues;
- July
18 Intervenors call for new seismic hearings based on new geological
relevations from a recent earthquake at Morgan Hill;
- July
23 The local district attorney files charges against PG&E for
a 1983 1/2 acre concrete spill while attempting to repair the breakwater;
- July
25 In a secret NRC meeting to discuss how to get around the formerly
agreed upon evacuation plans that were to have been in place prior to
licensing, NRC attorney Sheldon Trubatch says "We don't have to
look at earthquakes in California because we have determined that they
are not important to look at."
- July
30 The NRC releases 4 reports claiming unit 1 is ready to operate
and that all major issues have been resolved. They request PG&E
start a new study on Hosgri;
- Aug
2 The NRC votes 3-1 in favor of giving PG&E a full power license
for unit 1;
- Aug
7 Intervenors ask for an injunction from the U.S. Circuit Court
of Appeals in Washington D.C.; THE KEY LEGAL ISSUE AT STAKE In 1981,
the NRC refused to consider how an earthquake might effect evacuation
plans at San Onofre. Instead, it promised to deal with the issue in
for all of future licenses. But when Diablo was ready for approval in
1984, the commission had done nothing with the issue.
- Aug
9 The U.S. Circuit Court of Appeals in Washington, orders the NRC
to respond to the proposed injunction against Unit 1's full power license
by Aug 12;
- Aug
12 The NRC refuses Rep. Markey's request to hold emergency planning
hearings claiming the jurisdiction over the issue has passed to the
U.S. Court of Appeals;
- Aug
17 The Mothers for Peace gains a stay on the NRC's full power decision
from the U.S. Court of Appeals in Washington D.C.;
- Oct
27 A CPUC judge orders PG&E to preserve all documents related
to construction and safety issues at Diablo Canyon due to concerns that
the utility might be destroying documents;
- Oct
27 A N.Y. representative sends a letter to the NRC accusing the
agency of acting illegally in licensing Diablo without ordering evacuation
plans as promised;
- Oct
30 NRC Commissioner James Asselstine accuses fellow commisioners
of "serious abuses" in licensing Diablo Canyon;
- Oct
31 The U.S. Court of Appeals in Washington D.C. removes the federal
stay on full power operations for Diablo Canyon Unit 1 after the NRC
refused to release the controversial July 1984 transcripts;
- Nov
2 The NRC grants a full power operating license to PG&E;
- Nov
8 PG&E raises its estimated costs for Diablo to $5.3 billion.
The reactor is now operating at 2% of its rated capacity;
- Nov
13 A federal grand jury starts investigation into criminal allegations
of actions by the NRC;
1985
- Jan
9 PG&E requests a full power operating license for unit 2;
- Jan
10 KRON TV in S.F. reveals the secret NRC transcripts from 1984.
The transcripts show that: 1. the NRC based its decision on an unlitigated
PG&E evacuation plan; 2. the NRC expressed economic concerns if
the hearings were held over safety issues; 3. the NRC misled the U.S.
Court of Appeals by refusing to reveal the transcripts;
- Jan
10 The CPUC staff proposes a $170 million rate reduction for PG&E
ratepayers. PG&E requests a $219 million rate increase;
- April
PG&E is given permission by the NRC to start low-power testing
of unit 2;
- May
2 The D.C. federal appeals court votes 9-1 to reopen the Mothers
for Peace appeal of Diablo Canyon's operating license. The court refuses
to stop the reactor;
- May
7 Diablo Canyon unit 1 begins commercial operation;
- June
10 The CPUC estimates that Diablo will cause the loss of $120 million
in revenues from PG&E's natural gas sales;
- June
27 8 workers are charged with selling cocaine;
- July
10 The House of Representatives holds hearings on the NRC's licensing
of unit 1. Chairman Markey states that the secret transcripts "reminded
me of the Watergate tapes." The committee takes testimony from
the NRC and and opponents. A committee investigation is done finding
the NRC guilty of: 1. deliberately attempting to avoid public hearings
on evacuation planning; 2. considering off the record materials from
PG&E that had not been adjudicated; and 3. refusing hearings because
it would entail further delays and increased costs to PG&E;
- July
31 Value based pricing scheme for Diablo Canyon proposed by CPUC;
- Aug
1 The NRC approves a full-power operating license for Unit 2;
- Aug
2 Intervenors say they will challenge the operating license for
Unit 2;
- Aug
20 The Diablo Canyon unit 2 is started for the first time;
- Aug
21 CPUC allows PG&E to charge $716 million of the controversial
Helms River power project costs to ratepayers. The project uses excess
Diablo Canyon power as its primary power source;
- Aug
27 Unit 1 is shutdown for 2 days because of a breakdown in a steam
generator water pump;
- Sept
3 The Chair of a house sub-committee says that the NRC chairman
may have given his committee inaccurate testimony;
- Sept
10 The Santa Cruz supervisors will vote on a proposal calling for
the storage of all low-level wastes at Diablo;
- Sept
12 PG&E requests a $712 million yearly increase in electric
rates for Diablo;
- Sept
19 The state Pollution Control Financing Authority delays a decision
on PG&E's request to sell $109 million in bonds to modify waste
facililities at Diablo;
- Oct
8 PG&E loses its proposal to prevent public access to documents
that will be involved in the CPUC ratecase;
- Oct
17 PG&E also wants a $917 milliion rate increase for 1987;
- Oct
20 Unit 2 produces electricity for the first time;
- Nov
29 Unit 2 is shutdown by a monitor that detects a high steam flow;
- Dec
4 Seaweed forces the shutdown of both reactors;
- Dec
9 For the 3rd time in 2 years, security guards(4) are arrested for
selling cocaine;
- Dec
CPUC grants PG&E a $53.8 million rate increase to cover operating
costs at Diablo Canyon. The utility asked for $206 million. The CPUC
allows the utility to keep an estimated $334 million in fuel savings;
1986
- Jan
Republicans gain control over the CPUC assuring a major shift in policy
towards PG&E;
- April
25 The U.S. Court of Appeals votes 5-4 against the Mothers for
Peace request to open an investigation into the NRC's secret July 1984
transcripts and to stop the operation of the facility. The Majority
decision was written by Judge Robert Bork, the man who ordered the firing
of the Watergate prosecutor, and later proposed for a slot on the Supreme
Court by Ronald Reagan. The first of the two decisions, according to
Bork claimed that the court would be setting policy if it investigated
the secret transcripts. Then Bork used information from those very same
transcript, in the decision not to reverse the power license, saying
that the NRC had taken care of the seismic issues;
- April
26th 1:23 AM The Chernobyl reactor in the Ukraine blows up resulting
in the largest industrial disaster in human history;
- May
14 William Bennett asks the state Supreme Court to order the CPUC
to hold hearings on PG&E's evacuation plans;
- July
14 The First public broadcast in Northern California of David Brown's
"A Question of Power" (A brief history of Diablo) on a small
college station (KCSM);
- July
23 Democratic candidate for govenor Tom Bradley calls for new safety
rules at the state's reactors;
- July
24 The Mothers for Peace appeals the April court decision to the
Supreme Court;
- Aug
12 Intervenors win a court appeal to block PG&E's $16 million
reracking of spent fuel containers;
- Sept
16 The Sierra Club and Mothers for Peace file another restraining
order to stop PG&E's reracking of spent fuel;
- Sept
23 Intervenors reach an out of court settlement on PG&E's plans
to rerack spent fuel at Diablo Canyon;
- Oct
7 The CPUC starts the decommissioning ratemaking phase for Diablo
Canyon;
- Oct
20 The U.S. Supreme court refuses to reverse the April 25th, Court
of Appeals decision to allow Diablo Canyon to operate, ending legal
challenges of the operating license;
- Nov
14 NRC regional safety director states that PG&E's management
performance has slipped;
- Dec
6 PG&E may be fined by the NRC for its repeated failure to fix
a damaged door that is designed to prevent radiation releases;
- Dec
22 PG&E is given a $29 million rate increase to cover operating
costs of Diablo during the CPUC rate investigation;
1987
- Jan
2 A fire in Unit 1 injures two workers at the facility;
- Jan
5 A hydraulic leak shuts Unit 1 down;
- Feb
22 High water levels in the Unit 1 steam generator shuts down the
reactor. The reactor trips again after an attempt to restart it due
to a blown electrical circuit;
- Feb
PG&E donates $520,000 for new lights on the Golden Gate Bridge;
- Mar
7 The CPUC votes a $53.2 million a year increase to ratepayers
to create the Diablo Canyon decommissioning fund. The amount was based
on CPUC hearings that estimated the cost in 1987 dollars for closing
the facility at $587.6 million or $3.5 billion dollars in 2015 dollars;
- Mar
13 Diablo Canyon Unit 2 begins commercial operation;
- March
16 A small plane crashes into a high-voltage line 40 miles from
the reactors causing unit 1 to be shut down;
- Mar
20 Top NRC officials meet with PG&E management to discuss agency
concerns that the utility failed to operate the facility properly. There
are 14 allegations of harassment of workers and failure to report safety
violations in the last year;
- April
5 Unit 2 shuts down due to excessive buildup of steam in the turbine.
The unit will be closed for 12 weeks for refueling;
- April
10 15 workers were evacuated as a result of radioactive exposure
from Unit 2 during refueling. Radiation escapes outside and 30 gallons
of coolant spills inside;
- May
7 Unit 1 operates at 93% of it rated capacity during its first year
of operation-- a U.S. record;
- May
8 PG&E goes to the state Supreme Court, now that "liberal
justices" have been removed to get higher rates for Diablo from
earlier decisions;
- May
12 Both reactors were shut down, one for refueling and the other
due to problems in the power grid;
- May
15 The CPUC staff recommends that customers pay no more than $1.15
billion of the $5.52 billion costs, based upon its 3 year-$7.4 million
investigation that reviewed over 100 million documents that generated
a 17,000 page report on the reactors. The staff states that: 1. PG&E
failed to conduct studies of offshore earthquake faults or search out
data published in 1971 by Shell Oil Co. that identified the Hosgri Fault
three to five miles offshore from the plant. 2. From 1971-76, PG&E
repeatedly ignored or minimized evidence of the fault -- even though
PG&E's own consulting geologist acknowledged in 1973 that it might
be capable of a 7.5 magnitude quake -- and continued to construct the
plant as originally designed. 3. The company was slow and deficient
in implementing a quality assurance program after the 1976 redesign
was ordered. As a result, it failed to uncover a series of major design
errors.
- 4. PG&E
was forced to redo seismic modifications in 1982 after building them
backwards;
- June
The ASLB holds public hearings on PG&E's proposal to increase the
volume of spent fuel in storage ponds 5 fold. Out of 90 people attending,
only PG&E people were in favor;
- June
11 PG&E demands an immediate $257 million rate increase to help
cover operating costs at Diablo;
- June
17 180 of Diablo Canyon's security guards go on strike demanding
a 3% pay raise;
- June
19 PG&E announces the discovery of another "insignificant"
fault near the facility;
- June
20 PG&E workers end a 3 day strike with no terms disclosed;
- June
31 NRC reports that 2 of 3 barriers designed to prevent radiation
from leaking into the environment were not in place during a recent
accident at Unit 2;
- Sept
16 A CPUC judge opposes a plan to give PG&E $543 million a
year to cover construction costs at Diablo Canyon;
- Sept
26 State attorneys will ask an administrative law judge to rule
that customers aren't liable for $2.5 billion in operating delays at
Diablo;
- Oct
1 The CPUC judge blocks a staff proposal to disallow any of the
post 1982 construction costs ($2.5 billion) at Diablo Canyon;
- Oct
16 The CPUC refuses PG&E's request for an additional $266 million
rate increase to help pay for Diablo;
- Oct
28 PG&E wins a motion to contest the CPUC's plans to exclude
all costs after 1982;
- Nov
10 Diablo Canyon's emergency warning system accidently trips turning
on sirens throughout the county;
- Dec
10 The CPUC grants PG&E a rate increase that sets average electric
bill at $40.72 a month;
1988
- Jan
5 PUC staff requests a delay in the startup for the final rate hearings
as PG&E delivers 50 boxes of testimony and records to each of the
parties involved;
- Feb
3 A senior reactor operator at Diablo is reprimanded for doing unauthorized
work on a malfunctioning valve, leading to a reactor surge of 103% above
capacity;
- March
21 The state Supreme Court rules in favor of a 1985 rate increase
granted to PG&E by the CPUC;
- April
13 A CPUC judge supports a $147.2 million rate increase for PG&E
costs;
- May
11 The CPUC grants PG&E a $147.2 million rate increase for PG&E's
Diablo Canyon facility;
- June
19 The CPUC final rate hearings are delayed a week due to a settlement
between the PUC, PG&E and state Attorney General;
- June
28 State Attorney General Van De Kamp signs onto the proposed settlement
for Diablo Canyon;
- June
27 This is the headline that the San Jose Mercury News printed concerning
the proposed Diablo Canyon rate settlement. (Note that every major media
outlet made similar claims): REACTOR SETTLEMENT SHIFTS COSTS ONTO STOCKHOLDERS
Step forward into the future and find the truth;
- July
17 A series of electrical failures in Unit 2 causes the failure
of 3 of 4 coolant pumps. This results in an imbalance of steam in the
system that inturn initiated a safety backup system which shuts the
reactor down;
- Nov
31 The 9th U.S. Circuit Court of Appeals rules that the NRC failed
to properly consider safety issues for PG&E's spent fuel reracking
plan;
- Dec
19 "The state Public Utilities Commission today adopted an
unprecedented plan that forces PG&E to pay about $2.1 billion of
the cost of building the Diablo Canyon." This is how the public
trust was broadcast via the media. TURN got a couple of sentences in
like: ''It's a sellout of the consumers' interest,''. Opponents of the
settlement that had taken part in the 3 year hearings were simply brushed
aside by the media. There was NO real attempt to look closely at the
deal. Just what the proponents were claiming. See the Abalone Alliance
Press statement that was REFUSED to even be taken by the media at the
press conference. Press statement:
- Dec
24 PG&E discloses $500 million in write-offs that are allowed
as a result of the PG&E settlement. Additional write-offs are expected
next year;
1989
- Jan
11 The U.S. Supreme Court rules that consumers don't have to pay
any of the costs of abandoned nuclear power facilities;
- Jan
19 PG&E claims a $487 million loss in the 4th quarter of 1988
due to allowed Diablo Canyon write-offs;
- April
7 Former head of the CPUC William Bennett takes PUC settlement to
state supreme court;
- July
7 NRC proposes a $75,000 fine to PG&E for failure to place Unit
2 in hot shutdown when critical pumps were not working last January;
- July
18 Unit 2 is shut down to repair leaky ocean intake pipes;
- July
27 The state Supreme Court refuses to reverse the CPUC rate settlement
decision made on Dec. 1988;
- Sept
5 PG&E spends $20 million for a 5 years seismic study that is
now being looked at by the NRC and USGS. The study found 5 other faults
near the facility including the San Luis Bay Fault 1.2 miles from the
facility. The study claims the Hosgri fault did not cause the 1927 earthquake
that destroyed Lompoc Quake. The controversy on the length and type
of fault is still hotly disputed by experts from both sides. New key
to building safety is the frequency at which a building resonates during
a quake;
- Oct
20 Public Citizen calls for reopening seismic investigations at
Diablo Canyon and Millstone, both located near active faultlines;
- Oct
27 Unit 2 is shut down due to sparks spotted in the electric turbine;
- Oct
28 A Unit 2 Unusual Event declared when outside fire fighters are
called in to deal with a fire in the electrical generator;
- Dec
16 State Attorney General Van De Kamp refuses to appoint a nominee
to the Diablo Canyon Independent Safety Committee claiming that all
of the candidates were pro-nuclear(nominees were selected by PG&E,
dean of UC engineering Dept. & the CPUC president);
- Dec
20 PG&E is granted a $433 million rate increase by the CPUC;
1990
- Jan
3 Random drug testing for 1,900 employees of the facility are started(Union
employees were excluded due to a court order);
- Jan
18 PG&E posts a $901 million in profit for 1989, up from $62
million on 1988;
- Feb
14 The NRC fines PG&E $50,000 for a level 3 violation at the
facility;
- April
20 PG&E claims they had a 14% dip in profits during the 1st
quarter due to their routine refueling of one of the reactors;
- Apr
28 USGS is calling for seismic retrofits at Diablo due to an upgrade
in the Hosgri fault's potential dangers. The NRC and PG&E will release
a report in june;
- Oct
25 PG&E requests a $480 million rate increase from the CPUC;
- Dec
19 The CPUC grants PG&E a $668 million a year increase in rates
or over $8.00 a month increase for individual customers increases are
for farm subsidies and Diablo Canyon; Average bill will go from $51.97
to $58.30
- Dec
24 NRC launches a probe into a series of mechanical failures at
Unit 1;
1991
- May
17 A Diablo technician accidently removes the wrong fuses triggering
a shutdown;
- June
11 The NRC's review of a PG&E seismic study claims the facility
is safe, but requires some additional bracing on some safety equipment;
- Aug
15 A Unit 2 coolant pipe breaks, dumping several hundred gallons
of radioactive water into the containment building;
- Oct
17 PG&E says 3rd quarter earnings drop due to Unit 2's regular
refueling outage;
1992
- Jan
17 A small earthquake occurs offshore of Diablo Canyon at 12:36
AM;
- Sept
18 Towards Utility Rate Normalization (TURN) calls the 1988 rate
settlement "obscene" and demands the decision be reversed;
- Oct
19 The Hosgri fault is now believed to be a "thrust fault"
(as originally claimed by intervenors in 1978) by USGS. New information
from recent quakes has indicated that the reactors may not be strong
enough to survive a maximum credible event;
- Oct
19 NRC issues a bulletin that reveals that fire barriers at Diablo
and other reactors could fail to protect vital wiring;
1993
- Feb
6 Unit 1 is partially shutdown due to an overheated pump;
- Feb
15 The media starts reporting the impact of Diablo Canyon rates
on ratepayers;
- April
22 PG&E claims its earnings dropped 7.5% due to a regularly
scheduled refueling at Unit 2;
- Jun
10 PG&E agrees to freeze rates and layoff up to 2,600 workers
to help offsite growing rates caused by the 1988 Diablo Canyon rate
agreement;
- Aug
16 PG&E is requesting that expiration dates of the facility's
operating license-- to 2021 from 2008 for one reactor, and to 2025 from
2010 for the other;
1995
- May
24 The CPUC approves a 32% cut in Diablo Canyon rates TURN says
that $700 million of the reduction will be given to PG&E shareholders
to pay for the PG&E rate freeze. The CPUC staff based on current
operations projected that PG&E would recover all investments in
less than 15 years unless changed;
- July
2 The S.F. Examiner publishes a story about how S.F. Mayor Willie
Brown made a deal in 1988 to stop any state supported hearings on Diablo
Canyon in exchange for cutting a $3 million business deal to O.J. Simpson
lawyer Johnnie Cochran;
- Sept
30 Unit 1 is shut down for its regular refueling;
- Dec
2 Unit 1 was shut down due to pump problems;
1996
- Jan
24 The 9th District Court of Appeals reverses a lower federal court's
decision to grant $2 million in damages to a PG&E/Bechtel worker
who claimed he was caught in a PG&E drug sting and then fired;
Sources:
San Jose Mecury News, S.F. Examiner, San Luis Obispo Telegraph-Tribune,
Mark Evanoff, PG&E Testimony before the CPUC in case 84-06-014-Exhibit
1002 volume #2 October 1987, PUC staff testimony in case 84-06-014 Volume
#1, March 1987
|